Upload a P6 XER file and see what needs to be ordered this week so your schedule doesn't slip — every long-lead item ranked by float and days remaining until it's due on site.
Upload Programme
Programme (.xer)
Click or drop file
A single P6 export — not a before/after pair
Overdue
—
Due Within 14 Days
—
Matched Items
—
Data Date In Use
—
Two calendars are deliberately mixed here. "Date required on site" is the CPM engine's early-start date, computed on the project's working-day calendar. Lead time is subtracted in real calendar days, not workdays — suppliers don't work your site calendar. That's intentional, not a bug, but it means the order-by date won't match a naive hand calculation using only one calendar. Total float is likewise computed on the project's working-day calendar by the same engine FloatCheck uses — float calculated by the FloatCheck CPM engine.
Add / Edit Matches
Manually tag an activity (or re-tag one auto-matched incorrectly by adding it again with a different material)